The channel was identified as a recommended improvement during the process of receiving a 1041 Permit from Grand County during consideration of the Windy Gap Firming Project. On the East Slope, the project includes the construction of Chimney Hollow Reservoir west of Berthoud.
Sept. 1, 2022
Connectivity Channel Groundbreaking Celebrates Start of Project
Dignitaries from across the region gathered on Aug. 23 to celebrate the start of construction at the Colorado River Connectivity Channel located in Grand County. Led by U.S. Sen. Michael Bennet, leaders of public agencies and private non-governmental organizations extolled the value of the project that will reconnect two segments of the Colorado River above and below Windy Gap Reservoir.
Dirt was turned on the existing Windy Gap Dam, which lies on the Colorado River just west of the river’s confluence with the Fraser River. In the project, the existing dam’s length will be reduced by about 800 feet, and a new channel will direct water around the reservoir for most weeks of the year.
The project will take about three years to build, at a cost of nearly $30 million. Funding will come from many sources, including the USDA’s Natural Resources Conservation Service, Colorado Water Conservation Board, Northern Water, Municipal Subdistrict, Grand County, Trout Unlimited, Colorado Parks and Wildlife, Colorado River Water Conservation District, Upper Colorado River Association, National Fish and Wildlife Foundation and a number of corporate sponsors.