News
Final Chimney Hollow Virtual Tour
In the final virtual tour, the project team gives a look at the project nearly complete, as well as an overview on what it's like to demobilize a project of this size.
Initial Water Delivery into Chimney Hollow Reservoir Delayed
Northern Water and the Chimney Hollow participants have decided to allow more time to gather additional water quality data before initial delivery of water into Chimney Hollow Reservoir.
Chimney Hollow Reservoir Project Wins West Regional Dam Safety Award
The award recognizes projects that make exemplary contributions to the improvement of dam safety in the United States.
Downstream Tunnel Portal Gets Finishing Touches
The final touches on the downstream portal were added at the end of September and include the words “Chimney Hollow 2025” over the entrance.
Uranium Monitoring, Testing and Modeling Continue
We are following a rigorous process, starting with geochemical characterization and scoping studies, to inform mitigation alternatives analysis and ultimately select a final approach.
System to get Water in and Out of Chimney Hollow Nearly Complete
The water conveyance system used for delivering water in and out of Chimney Hollow Reservoir is constructed and nearly complete.
More Than 35,000 Cubic Yards of Concrete Placed at Chimney Hollow
Concrete was used in almost every area of the project, including the plinth, spillway, thrust blocks, valve house, tunnel lining, inlet/outlet, tower, staff gauge and more.
Chimney Hollow Main Dam Complete
The tallest new dam built in the United States in the last 25 years is now complete. Crews celebrated the huge milestone during an all-site safety meeting on Aug. 7.
Final Asphalt Placed on the Main Dam
After 1,000 days, 3.3 million work hours and 512 lifts encompassing 200 miles of asphalt paving, a huge milestone was reached on Friday, July 18, as crews placed the final lift of asphalt.