Reservoir on Track to Finish in Late Summer 2025
As Chimney Hollow reaches 30 months of construction, Northern Water’s Municipal Subdistrict staff, along with key project contractors, anticipate completion of the reservoir in late summer 2025.
Chimney Hollow Rises Above 150 Feet Tall in 2023
With more than two years of construction in the rearview mirror, Chimney Hollow Reservoir is rising quickly to meet the challenges of providing resilient water supplies.

Progress Continues on Concrete Spillway
Throughout the past year, crews have been working on the reinforced concrete spillway on the left (west) abutment of the main dam.

Winter Construction and Its Challenges
One of the greatest challenges crews face during the construction of Chimney Hollow Reservoir is winter weather.

Employee Spotlight: Melanie Wilcox
Melanie Wilcox plays an integral role for the Chimney Hollow Reservoir Project as Barnard Construction’s lead haul truck trainer.

Grand County Organizations Awarded Grants in Second Year of Funding
In its second year of grant funding, the Windy Gap Environmental Fund (WGEF) has awarded four Grand County organizations funds for various environmental projects.

Participant Profile: City of Fort Lupton
About 43 miles southeast of the Chimney Hollow Reservoir Project sits the growing city of Fort Lupton with a current population of just over 8,500.

Employee Spotlight: Christina Brueckman
Christina Brueckman serves as Stantec’s Lead Geological Engineer and Resident Deputy Engineer for the Chimney Hollow Reservoir Project.

Safety Remains Top Priority on Site
General contractor Barnard Construction employs a full-time, on-site safety team dedicated to providing proper training for all individuals, as well as adhering to safety protocols.