Construction of Spillway Channel Features Underway
While excavation of the spillway channel has been ongoing for over a year, crews recently made the first concrete placements, including shear keys, a seepage cutoff wall and spillway underdrains.
Loveland Fire Rescue Authority Crews Attend Quarterly Site Visits
It is critical to keep local first responders up to date on how to navigate the ever-evolving construction site and make them aware of current hazards on site to help them quickly respond to calls.
Key Milestones Achieved at Chimney Hollow Reservoir in 2022
Chimney Hollow Reservoir construction crews made significant progress in 2022. Work started in August 2021 and is scheduled to continue until August 2025.