Crews work on the foundation of Green Mountain Dam on June 22, 1942.
Building Colorado’s Largest Transmountain Diversion Project
The U.S. Bureau of Reclamation oversaw construction of more than 100 features and facilities that make up the C-BT Project. Work began in 1938 and took nearly 20 years to complete. While the final price tag for project construction was nearly $162 million, it is regarded by many as a great bargain for Northern Colorado residents.
Crews began work in 1938 on Green Mountain Reservoir, which stores water to compensate the West Slope for the water diverted to the East Slope. During the next two decades, C-BT Project construction yielded several significant historical moments and plenty of challenges.
Construction of the Alva B. Adams Tunnel began on June 23, 1940. Contractors bored the tunnel simultaneously from both portals, and when the two crews met beneath the Continental Divide on June 10, 1944, the alignment was off by less than the width of a penny.
The first Colorado River water reaches the East Portal of the Adams Tunnel on June 23, 1947.
First Water Delivered in 1947
The first interim water deliveries from the C-BT Project began in 1947. Reclamation declared the project to be substantially complete in 1957, the first year of full water deliveries.
As the largest transmountain water diversion project in Colorado, today the C-BT Project provides supplemental water to 33 municipalities and 120 ditch, reservoir and irrigation companies that supply approximately 550,000 acres of Northeastern Colorado farmland.
The project consists of 12 reservoirs, 35 miles of tunnels, 95 miles of canals and 700 miles of transmission lines. Overall, the system spans 150 miles east to west and 65 miles north to south.